$A$ and $B$ can do a piece of work in $20$ days and $12$ days respectively. $A$ started the work alone and then after $4$ days $B$ joined him until the completion of the work. How long did the work last? (in days)

  • A
    $10$
  • B
    $20$
  • C
    $15$
  • D
    $6$

Explore More

Similar Questions

Subhash can copy $50$ pages in $10$ $h$,Subhash and Prakash can copy $300$ pages in $40$ $h$. In how much time can Prakash copy $30$ pages? (in $h$)

$A$ is thrice as good a workman as $B$,therefore,$A$ is able to finish a piece of work in $60 \, days$ less than $B$. The time (in $days$) in which they can do it working together is

Difficult
View Solution

$A$'s $2$ days work is equal to $B$'s $3$ days work. If $A$ can complete the work in $8$ days,then to complete the work $B$ will take (in days):

$A$ and $B$ can together complete a task in $18$ hours. After $6$ hours, $A$ leaves. $B$ takes $36$ hours to finish the rest of the task. How many hours would $A$ have taken to do the task if he worked alone?

Three men,four women and six children can complete a work in $7$ days. $A$ woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in $7$ days?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo