$A$ and $B$ working separately can do a piece of work in $9$ and $12$ days,respectively. If they work for a day alternatively with $A$ beginning,the work would be completed in (in days):

  • A
    $10 \frac{2}{3}$
  • B
    $10 \frac{1}{2}$
  • C
    $10 \frac{1}{4}$
  • D
    $10 \frac{1}{3}$

Explore More

Similar Questions

$A$ can do a work in $6$ days and $B$ can do the same work in $5$ days. The contract for the work is of $Rs. 220$. How much shall $B$ get if both of them work together? (in $Rs.$)

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

$P, Q, R$ are employed to do a work for $Rs. 5750$. $P$ and $Q$ together finished $\frac{19}{23}$ of the work,and $Q$ and $R$ together finished $\frac{8}{23}$ of the work. The wage of $Q$ (in rupees) is:

$P, Q$ and $R$ contract a work for $Rs. 550$. Together,$P$ and $Q$ are supposed to do $\frac{7}{11}$ of the work. How much does $R$ get? (in $Rs.$)

$P$ and $Q$ complete a certain work in $30 \, days$,$Q$ and $R$ in $40 \, days$,while $R$ and $P$ in $60 \, days$. How long will they take to finish it together? (in $days$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo