$P$,$Q$ and $R$ contracted to do a work for $Rs. 4200$. $P$ can do the work in $6$ days,$Q$ in $10$ days and $R$ in $12$ days. If they work together to do the work,what is the share of $R$ (in $Rs.$)?

  • A
    $2000$
  • B
    $1200$
  • C
    $1000$
  • D
    $1500$

Explore More

Similar Questions

$A$ and $B$ together can complete a work in $8$ days. $B$ alone can complete that work in $12$ days. $B$ alone worked for $4$ days. After that,how long will $A$ alone take to complete the remaining work?

$A$ worker can complete a piece of work in $50$ days. On the first day,he works alone. On the second day,one more person joins him,on the third day,one more person joins them,and this process continues until the work is completed. How many days are needed to complete the work?

$P$ can complete $\frac{1}{4}$ of a work in $10$ days,$Q$ can complete $40\%$ of the same work in $15$ days,$R$ can complete $\frac{1}{3}$ of the work in $13$ days,and $S$ can complete $\frac{1}{6}$ of the work in $7$ days. Who will be able to complete the work first?

$A, B$,and $C$ are employed to do a piece of work for $Rs. 529$. $A$ and $B$ together are supposed to do $\frac{19}{23}$ of the work,and $B$ and $C$ together are supposed to do $\frac{8}{23}$ of the work. What amount should $A$ be paid? (in $Rs.$)

$A$ and $B$ can do a work in $12$ days. $B$ and $C$ can do the same work in $15$ days. $C$ and $A$ can do the same work in $20$ days. How much time will $A, B,$ and $C$ take to complete the same work together (in days)?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo