$A$ and $B$ working separately can do a piece of work in $10 \text{ days}$ and $15 \text{ days}$ respectively. If they work on alternate days beginning with $A$,in how many days will the work be completed?

  • A
    $18$
  • B
    $13$
  • C
    $12$
  • D
    $6$

Explore More

Similar Questions

Some carpenters promised to do a job in $9$ days,but $5$ of them were absent and the remaining men did the job in $12$ days. The original number of carpenters was:

$A$ is $30\%$ more efficient than $B.$ How much time will they,working together,take to complete a job which $A$ alone could have done in $23$ days? (in days)

Difficult
View Solution

Bindal can finish a work in $10$ days. Jindal is twice as efficient as Bindal. If they work together,in how many days will the work be completed?

If $A$ and $B$ together can complete a work in $18$ days,$A$ and $C$ together in $12$ days,and $B$ and $C$ together in $9$ days,then $B$ alone can do the work in (in days)

$A$ and $B$ can do a work in $12$ days,$B$ and $C$ in $15$ days,and $C$ and $A$ in $20$ days. If $A, B,$ and $C$ work together,they will complete the work in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo