$A$ and $B$ working separately can do a piece of work in $9$ and $15 \, \text{days}$ respectively. If they work on alternate days beginning with $A$,then the work will be completed in how many days?

  • A
    $10$
  • B
    $11$
  • C
    $9$
  • D
    $12$

Explore More

Similar Questions

$2$ men alone or $3$ women alone can complete a piece of work in $4$ days. In how many days can $1$ woman and $1$ man together complete the same piece of work?

$A, B$ and $C$ can do a job in $6$ days,$12$ days and $15$ days,respectively. After $\frac{1}{8}$ of the work is completed,$C$ leaves the job. The rest of the work is done by $A$ and $B$ together. The total time taken to finish the work is (in days):

$A$ can do $\frac{1}{4}$ of a work in $10$ days. $B$ can do $\frac{1}{3}$ of the work in $20$ days. In how many days can both $A$ and $B$ together do the work?

$A$ man,a woman,and a boy can complete a job in $3, 4,$ and $12$ days respectively. How many boys must assist $1$ man and $1$ woman to complete the job in $\frac{1}{4}$ of a day?

Difficult
View Solution

Subhash can copy $50$ pages in $10$ $h$,Subhash and Prakash can copy $300$ pages in $40$ $h$. In how much time can Prakash copy $30$ pages? (in $h$)

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo