$A$ and $B$ can do a piece of work in $12 \, \text{days}$ and $15 \, \text{days}$ respectively. They began to work together,but $A$ left after $4 \, \text{days}$. In how many more $days$ would $B$ alone complete the remaining work?

  • A
    $20/3$
  • B
    $25/3$
  • C
    $6$
  • D
    $5$

Explore More

Similar Questions

$A$ can lay railway track between two given stations in $16 \, days$ and $B$ can do the same job in $12 \, days$. With the help of $C$,they did the job in $4 \, days$ only. Then $C$ alone can do the job in (in $days$)

$A$ can do a piece of work in $4 \, days$ and $B$ can do it in $12 \, days.$ In how many $days$ will they finish the work,both working together?

$20$ men can complete a piece of work in $16$ days. After $5$ days from the start of the work,some men left. If the remaining work was completed by the remaining men in $18 \frac{1}{3}$ days,how many men left after $5$ days from the start of the work?

$A$ and $B$ can complete a piece of work in $45$ and $40$ days respectively. Both started to work together,but after some days $A$ left and $B$ alone completed the remaining work in $23$ days. For how many days did $A$ work?

Difficult
View Solution

$A$ can do a job in $6 \, days$ and $A$ and $B$ can do it together in $2 \, days.$ How many $days$ will be taken by $B$ to do the job alone?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo