$P$ is twice as good a workman as $Q,$ and together they finish a work in $16$ days. In how many days can it be done by each separately?

  • A
    $16, 24$
  • B
    $24, 48$
  • C
    $20, 40$
  • D
    $24, 16$

Explore More

Similar Questions

$A$ and $B$ can do a piece of work in $18$ days,$B$ and $C$ in $24$ days,and $A$ and $C$ in $36$ days. In what time can they do it all working together? (in days)

Difficult
View Solution

$6$ men or $12$ women can do a piece of work in $20$ days. In how many days can $8$ men and $16$ women do twice as big as this work?

$A$ can finish a work in $18$ days and $B$ can do the same work in $15$ days. $B$ worked for $10$ days and left the job. In how many days can $A$ alone finish the remaining work?

$A$ does half as much work as $B$ in $three-fourths$ of the time. If together they take $18$ days to complete a work,how much time shall $B$ take to do it alone? (in days)

$A$ farmer can plough a field working $6 \text{ hours per day}$ in $18 \text{ days}$. How many $\text{hours per day}$ must the farmer work to finish the same work in $12 \text{ days}$?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo