$12$ men can complete a piece of work in $4$ days,while $15$ women can complete the same work in $4$ days. $6$ men start working on the job and after working for $2$ days,all of them stopped working. How many women should be put on the job to complete the remaining work,if it is to be completed in $3$ days?

  • A
    $15$
  • B
    $18$
  • C
    $22$
  • D
    Data inadequate

Explore More

Similar Questions

$2$ men and $5$ women can finish a piece of work in $12$ days. $5$ men and $2$ women can finish the same work in $9$ days. In how many days can $3$ women finish the same work?

$4$ men and $6$ women earn $Rs. \, 1600$ by doing a piece of work in $5$ days. $3$ men and $7$ women earn $Rs. \, 1740$ by doing the same work in $6$ days. In how many days can $7$ men and $6$ women complete the same work while earning $Rs. \, 3760$?

Difficult
View Solution

$A$ can do a certain work in $12$ days. $B$ is $60\%$ more efficient than $A$. How many days will $B$ and $A$ together take to do the same job?

$P, Q$ and $R$ can do a piece of work in $60$ days,$100$ days and $80$ days respectively. They work together to finish the work and receive $Rs. 2256$. Then $P$ will get (in $Rs.$)

Difficult
View Solution

$P$ and $Q$ can do a piece of work in $30$ and $40$ days respectively. They began the work together,but $P$ left after some days and $Q$ finished the remaining work in $12$ days. After how many days did $P$ leave?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo