$A$ can do a piece of work in $14$ days,which $B$ can do in $21$ days. They begin together,but $3$ days before the completion of the work,$A$ leaves. The total number of days to complete the work is:

  • A
    $6 \frac{3}{5}$
  • B
    $8 \frac{1}{2}$
  • C
    $10 \frac{1}{5}$
  • D
    $13 \frac{1}{2}$

Explore More

Similar Questions

$45$ men can complete a work in $16$ days. Four days after they started working,$36$ more men joined them. How many days will they now take to complete the remaining work?

Difficult
View Solution

$A$ does $\frac{1}{5}$ of a work in a $week$. $B$ finishes the same in a fortnight. $B$ starts the work and works only for $3$ days. Thereafter,$A$ completes the job. In how many days will $A$ finish the remaining work?

If $10$ persons can do a job in $20$ days,then $20$ persons with twice the efficiency can do the same job in (in days)

If $A$ had worked alone, he would have taken $63 \, \text{hours}$ to complete the task. If $A$ and $B$ work together, they finish the task in $36 \, \text{hours}$. If they are paid $Rs. 5,950$ for the work, what is $B$'s share?

$2$ men and $3$ women can complete a work in $10$ days,while $4$ men can complete it in $10$ days. In how many days will $3$ men and $3$ women complete the work?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo