$A$ and $B$ can do a piece of work in $30$ days,while $B$ and $C$ can do the same work in $24$ days and $C$ and $A$ in $20$ days. They all work together for $10$ days when $B$ and $C$ leave. How many days more will $A$ take to finish the work?

  • A
    $18$
  • B
    $24$
  • C
    $30$
  • D
    $36$

Explore More

Similar Questions

Working efficiencies of $A$ and $B$ for completing a piece of work are in the ratio $3: 4$. The number of days taken by them to complete the work will be in the ratio:

$A, B$ and $C$ can do a piece of work individually in $8, 10$ and $15$ days respectively. $A$ and $B$ start working,but $A$ quits after working for $2$ days. After this,$C$ joins $B$ until the completion of the work. In how many days will the work be completed?

If $5$ men and $3$ boys can reap $23 \text{ hectares}$ in $4 \text{ days}$ and if $3$ men and $2$ boys can reap $7 \text{ hectares}$ in $2 \text{ days}$,how many boys must assist $7$ men in order that they may reap $45 \text{ hectares}$ in $6 \text{ days}$?

Difficult
View Solution

$A$ alone can do a piece of work in $6$ days and $B$ alone in $8$ days. $A$ and $B$ undertook to do it for $Rs. 3200$. With the help of $C$,they completed the work in $3$ days. How much is to be paid to $C$ (in $Rs.$)?

Difficult
View Solution

$A$ contract is to be completed in $50 \text{ days}$ and $105 \text{ men}$ were set to work,each working $8 \text{ hours a day}$. After $25 \text{ days}$,$\frac{2}{5}$ of the work is finished. How many additional men must be employed so that the work may be completed on time,with each man now working $9 \text{ hours a day}$?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo