$A$ can complete a work in $10$ days,$B$ can complete the same work in $20$ days,and $C$ in $40$ days. $A$ starts working on the first day,$B$ works on the second day,and $C$ works on the third day. Again,$A$ works on the fourth day,$B$ on the fifth day,and so on. If they continue working in the same way,in how many days will the work be completed?

  • A
    $15$
  • B
    $16.5$
  • C
    $15.5$
  • D
    $17$

Explore More

Similar Questions

$A$ can do a piece of work in $4\, h$,$B$ and $C$ can do it in $3\, h$,and $A$ and $C$ can do it in $2\, h$. How long will $B$ alone take to do it? (in $h$)

$4$ men or $6$ women or $10$ children can paint a house in $5$ days. The painting is given to a couple (a man and a woman) and their $5$ sons. They finish the job in (in days):

Two workers $A$ and $B$ working together completed a job in $5$ days. If $A$ worked twice as efficiently as he actually did and $B$ worked $1/3$ as efficiently as he actually did,the work would have been completed in $3$ days. To complete the job alone,$A$ would require (in days):

$A, B$ and $C$ can do a piece of work in $20, 30$ and $60$ days respectively. In how many days can $A$ do the work if he is assisted by $B$ and $C$ on every third day?

Difficult
View Solution

$A, B$ and $C$ can do a piece of work in $30, 20$ and $10$ days respectively. $A$ is assisted by $B$ on one day and by $C$ on the next day,alternately. How long would the work take to finish? (in days)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo