$A$ can finish a work in $24$ days,$B$ in $9$ days and $C$ in $12$ days. $B$ and $C$ start the work but are forced to leave after $3$ days. The remaining work was done by $A$ in (in days):

  • A
    $5$
  • B
    $6$
  • C
    $10$
  • D
    $10\frac{1}{2}$

Explore More

Similar Questions

Sixteen men can complete a work in $15$ days,$24$ children can do the same work in $20$ days. In how many days will $8$ men and $8$ children complete the same work?

Difficult
View Solution

The total number of men,women,and children working in a factory is $18$. They earn $Rs. 4000$ in a day. If the sum of the wages of all men,all women,and all children is in the ratio $18: 10: 12$,and the wages of an individual man,woman,and child are in the ratio $6: 5: 3$,then how much does a woman earn in a day? (in $Rs.$)

$A$ and $B$ can complete a piece of work in $6$ days,and $A$ alone can complete it in $9$ days. The time taken by $B$ alone to complete the work is (in days):

If $x$ men can do a piece of work in $x$ days,then the number of days in which $y$ men can do the same work is (in days)

$A$ can do a piece of work in $16$ days and $B$ in $24$ days. They take the help of $C$ and all three together finish the work in $6$ days. If the total remuneration for the work is $Rs. 400$,what is the amount (in $Rs.$) each will receive in proportion to the work done?

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo