$A$ contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹ $200$ for the first day,₹ $250$ for the second day,₹ $300$ for the third day,etc. The penalty for each succeeding day is ₹ $50$ more than for the preceding day. How much money does the contractor have to pay as a penalty if he has delayed the work by $30$ days?

  • A
    $27743$
  • B
    $27891$
  • C
    $27653$
  • D
    $27750$

Explore More

Similar Questions

Show that $a_{1}, a_{2}, \ldots, a_{n}, \ldots$ form an $AP$ where $a_{n}$ is defined as $a_{n}=9-5n$. Find the sum of the first $15$ terms.

Difficult
View Solution

Find the number of terms in the following $AP$: $18, 15 \frac{1}{2}, 13, \ldots, -47$.

Which term of the $AP: 3, 15, 27, 39, \ldots$ will be $132$ more than its $54^{th}$ term?

Difficult
View Solution

The taxi fare after each $km$ when the fare is ₹ $15$ for the first $km$ and ₹ $8$ for each additional $km$. Does the list of numbers involved form an arithmetic progression,and why?

The cost of digging a well after every metre of digging, when it costs ₹ $150$ for the first metre and rises by ₹ $50$ for each subsequent metre, does the list of numbers involved make an arithmetic progression, and why?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo