$A$ manufacturer produces nuts and bolts. It takes $1\, hour$ of work on machine $A$ and $3\, hours$ on machine $B$ to produce a package of nuts. It takes $3\, hours$ on machine $A$ and $1\, hour$ on machine $B$ to produce a package of bolts. He earns a profit of $Rs.\,17.50$ per package on nuts and $Rs.\,7$ per package on bolts. How many packages of each should be produced each day so as to maximise his profit,if he operates his machines for at the most $12\, hours$ a day?

Vedclass pdf generator app on play store
Vedclass iOS app on app store
(B) Let the manufacturer produce $x$ packages of nuts and $y$ packages of bolts.
Therefore,$x \geq 0$ and $y \geq 0$.
The given information can be compiled in a table as follows:
MachineNutsBoltsAvailability
Machine $A$ $(h)$$1$$3$$12$
Machine $B$ $(h)$$3$$1$$12$

The profit on a package of nuts is $Rs.\,17.50$ and on a package of bolts is $Rs.\,7$. Therefore,the constraints are:
$x + 3y \leq 12$
$3x + y \leq 12$
Total profit,$Z = 17.5x + 7y$.
The mathematical formulation of the given problem is:
Maximise $Z = 17.5x + 7y$ subject to the constraints:
$x + 3y \leq 12$
$3x + y \leq 12$
$x, y \geq 0$
The feasible region determined by the system of constraints has corner points $O(0,0)$,$A(4,0)$,$B(3,3)$,and $C(0,4)$.
The values of $Z$ at these corner points are as follows:
Corner point$Z = 17.5x + 7y$
$O(0,0)$$0$
$A(4,0)$$70$
$B(3,3)$$73.5$ (Maximum)
$C(0,4)$$28$

The maximum value of $Z$ is $Rs.\,73.50$ at $(3,3)$.
Thus,$3$ packages of nuts and $3$ packages of bolts should be produced each day to get the maximum profit of $Rs.\,73.50$.

Explore More

Similar Questions

The maximum value of the objective function $z=4x+6y$ subject to the constraints $3x+2y \leq 12$,$x+y \geq 4$,$x, y \geq 0$ is

For the inequalities $x+y \leq 3$,$2x+5y \geq 10$,$x \geq 0$,$y \geq 0$,which of the following points lies in the feasible region?

$A$ manufacturer has three machines $I, II$ and $III$ installed in his factory. Machines $I$ and $II$ are capable of being operated for at most $12 \, hours$ whereas machine $III$ must be operated for at least $5 \, hours$ a day. She produces only two items $M$ and $N$ each requiring the use of all the three machines. The number of hours required for producing $1$ unit of each of $M$ and $N$ on the three machines are given in the following table:
ItemsMachine $I$Machine $II$Machine $III$
$M$$1$$2$$1$
$N$$2$$1$$1.25$

She makes a profit of $Rs. \, 600$ and $Rs. \, 400$ on items $M$ and $N$ respectively. How many of each item should she produce so as to maximise her profit assuming that she can sell all the items that she produced? What will be the maximum profit?

Difficult
View Solution

$A$ factory makes tennis rackets and cricket bats. $A$ tennis racket takes $1.5\, \text{hours}$ of machine time and $3\, \text{hours}$ of craftsman's time in its making, while a cricket bat takes $3\, \text{hours}$ of machine time and $1\, \text{hour}$ of craftsman's time. In a day, the factory has the availability of not more than $42\, \text{hours}$ of machine time and $24\, \text{hours}$ of craftsman's time. What number of rackets and bats must be made if the factory is to work at full capacity?

Difficult
View Solution

In $L.P.P.$,the maximum value of the objective function $Z = 6x + 3y$ subject to the constraints $x + y \leq 5$,$x + 2y \geq 4$,$4x + y \leq 12$,$x, y \geq 0$ is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo