$A$ piece of work was to be completed in $40$ days. $A$ number of men employed upon it did only half the work in $24$ days. $16$ more men were then set on,and the work was completed in the specified time. How many men were employed at first?

  • A
    $16$
  • B
    $32$
  • C
    $24$
  • D
    $48$

Explore More

Similar Questions

If $12$ men and $16$ boys can do a piece of work in $5 \, \text{days}$,and $13$ men and $24$ boys can do it in $4 \, \text{days}$,then the ratio of the daily work done by a man to that of a boy is:

$A$ can do a work in $12$ days. When he had worked for $3$ days,$B$ joined him. If they complete the work in $3$ more days,in how many days can $B$ alone finish the work?

$A$ man,a woman,and a boy can together complete a piece of work in $3$ days. If a man alone can do it in $6$ days and a boy alone in $18$ days,how long will a woman alone take to complete the work? (in days)

$A$ and $B$ can complete a piece of work in $30 \text{ days}$,$B$ and $C$ in $40 \text{ days}$,while $C$ and $A$ in $60 \text{ days}$. $A, B, C$ together can complete the work in (in $\text{days}$):

$A$ is twice as good a workman as $B$. Working together,they finish a piece of work in $1.5$ days. $A$ alone can finish the work in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo