Working $7\, \text{hours}$ daily,$24$ men can complete a piece of work in $27$ $\text{days}$. In how many $\text{days}$ would $14$ men complete the same piece of work working $9\, \text{hours}$ daily?

  • A
    $36$
  • B
    $30$
  • C
    $32$
  • D
    None of these

Explore More

Similar Questions

$A$ can do a piece of work in $12$ days and $B$ in $20$ days. If they together work on it for $5$ days and the remaining work is completed by $C$ in $3$ days, then in how many days can $C$ do the same work alone?

$A$ can do a work in $15 \text{ days}$ and $B$ in $20 \text{ days}$. If they work together on it for $4 \text{ days}$,then the fraction of the work that is left is

$A$ and $B$ can complete a piece of work in $15$ days and $10$ days respectively. They contracted to complete the work for $Rs. 30000$. The share of $A$ in the contracted money will be (in $Rs.$)

$A$ and $B$ can complete a piece of work in $45$ and $40$ days respectively. Both started to work together,but after some days $A$ left and $B$ alone completed the remaining work in $23$ days. For how many days did $A$ work?

Difficult
View Solution

$10$ men working $6\, \text{h}$ a day can complete a work in $18\, \text{days}$. How many $\text{hours per day}$ must $15$ men work to complete the same work in $12\, \text{days}$?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo