$P, Q$ and $R$ can finish a work in $10, 12$ and $15$ days respectively. If $Q$ stops after $2$ days,how long would it take $P$ and $R$ to finish the remaining work? (in days)

  • A
    $6$
  • B
    $4$
  • C
    $3$
  • D
    $2$

Explore More

Similar Questions

Sita takes twice as much time as Gita to complete a work and Rita does it in the same time as Sita and Gita together. If all three working together can finish the work in $6$ days,then the time taken by each of them to finish the work is (in days):

Difficult
View Solution

Akka can bake $100$ cakes in $20$ hours. Akka and Tai together can bake $75$ cakes in $10$ hours. How many cakes can Tai bake in $20$ hours?

$A$ and $B$ together can do a piece of work in $9$ days. If $A$ does thrice the work of $B$ in a given time,the time $A$ alone will take to finish the work is (in days)

$A, B$ and $C$ can complete a piece of work in $24, 6$ and $12 \text{ days}$ respectively. Working together,they will complete the same work in (in $\text{days}$):

$A, B$ and $C$ can do a piece of work in $30, 20$ and $10$ days respectively. $A$ is assisted by $B$ on one day and by $C$ on the next day,alternately. How long would the work take to finish? (in days)

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo