$A$ and $B$ can do a work in $8$ days,$B$ and $C$ can do the same work in $12$ days. $A, B$ and $C$ together can finish it in $6$ days. $A$ and $C$ together will do it in (in days):

  • A
    $4$
  • B
    $6$
  • C
    $8$
  • D
    $12$

Explore More

Similar Questions

$10$ women can complete a work in $7$ days and $10$ children take $14$ days to complete the work. How many days will $5$ women and $10$ children take to complete the work?

$A$ and $B$ can complete a piece of work in $30 \text{ days}$,$B$ and $C$ in $40 \text{ days}$,while $C$ and $A$ in $60 \text{ days}$. $A, B, C$ together can complete the work in (in $\text{days}$):

Amit and Sujit together can complete a data entry assignment in $5$ days. Sujit's speed is $80\%$ of Amit's speed and the total key depressions in the assignment are $5,76,000$. What is Amit's speed in key depressions per hour if they work for $8$ hours a day?

$A$ contractor undertakes to dig a canal $12 \, km$ long in $350 \, days$ and employs $45$ men. After $200 \, days$ he finds that only $4.5 \, km$ of the canal has been completed. Find the number of extra men he must employ to finish the work in time (in $men$).

$A$ can complete a piece of work in $12$ days. $B$ is $60\%$ more efficient than $A$. The number of days that $B$ will take to complete the same work is:

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo