$A$ and $B$ undertake a piece of work for $Rs. 250$. $A$ alone can do that work in $5$ days and $B$ alone can do that work in $15$ days. With the help of $C$,they finish the work in $3$ days. If everyone gets paid in proportion to the work done by them,the amount $C$ will get is (in $Rs.$)

  • A
    $50$
  • B
    $100$
  • C
    $150$
  • D
    $200$

Explore More

Similar Questions

$A$ daily-wage labourer was engaged for a certain number of days for $Rs. 5,750$ but being absent on some days he was paid only $Rs. 5,000$. What was his maximum possible daily wage? (in $Rs.$)

$A$ can do a certain work in the same time in which $B$ and $C$ together can do it. If $A$ and $B$ together could do it in $10 \text{ days}$ and $C$ alone in $50 \text{ days}$,then $B$ alone could do it in (in $\text{days}$):

Difficult
View Solution

$10$ men can complete a piece of work in $15$ days and $15$ women can complete the same work in $12$ days. If all the $10$ men and $15$ women work together,in how many days will the work be completed?

$A$ can finish a work in $18$ days and $B$ can do the same work in half the time taken by $A$. Then,working together,what part of the same work can they finish in a day?

$A$ can finish a work in $24$ days,$B$ in $9$ days and $C$ in $12$ days. $B$ and $C$ start the work but are forced to leave after $3$ days. The remaining work was done by $A$ in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo