$P$ and $Q$ together can do a job in $6$ days. $Q$ and $R$ can finish the same job in $60/7$ days. $P$ started the work and worked for $3$ days. $Q$ and $R$ continued for $6$ days. Then the difference of days in which $R$ and $P$ can complete the job is

  • A
    $12$
  • B
    $10$
  • C
    $8$
  • D
    $15$

Explore More

Similar Questions

$A$ can do a work in $12 \, days$. When he had worked for $3 \, days$,$B$ joined him. If they complete the work in $3$ more $days$,in how many $days$ can $B$ alone finish the work?

Difficult
View Solution

$P$ can do $\left(\frac{1}{4}\right)$ of the work in $10$ days. $Q$ can do $40\%$ of the work in $40$ days and $R$ can do $\left(\frac{1}{3}\right)$ of the work in $13$ days. Who will complete the work first?

$A$ daily-wage labourer was engaged for a certain number of days for $Rs. 5,750$ but being absent on some days he was paid only $Rs. 5,000$. What was his maximum possible daily wage? (in $Rs.$)

Rohan and Mohit can build a wall in $8 \, days$,Mohit and Vikas can build the same wall in $10 \, days$,and Vikas and Rohan can build the same in $12 \, days$. In how many days can all three complete the same wall while working together?

Difficult
View Solution

$A$ farmer can plough a field working $6$ hours per day in $18$ days. How many hours per day must the farmer work to finish the same work in $12$ days?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo