$A$ can do a piece of work in $15 \text{ days}$. With the help of $A$,$B$ can do it in $6 \frac{2}{3} \text{ days}$. $B$ can do it alone in (in $\text{days}$)

  • A
    $13$
  • B
    $8$
  • C
    $10$
  • D
    $12$

Explore More

Similar Questions

$A$ and $B$ together can complete a work in $10$ days. They started together,but $A$ left after $2$ days and the remaining work was completed by $B$ in $12$ days. In how many days can $A$ complete the entire work while working alone?

Difficult
View Solution

$A$ and $B$,working together,can complete a piece of work in $12$ days. $B$ and $C$ working together can complete the same piece of work in $16$ days. $A$ worked at it for $5$ days and $B$ worked at it for $7$ days. $C$ finished the remaining work in $13$ days. How many days would $C$ alone take to complete it?

Difficult
View Solution

$P$ and $Q$ can do a piece of work in $30$ and $40$ days respectively. They began the work together,but $P$ left after some days and $Q$ finished the remaining work in $12$ days. After how many days did $P$ leave?

$2$ men alone or $3$ women alone can complete a piece of work in $4$ days. In how many days can $1$ woman and $1$ man together complete the same piece of work?

$A$ completes a piece of work in $4 \text{ days}$ and $B$ completes it in $6 \text{ days}$. If they both work on it together,then the number of days required to complete the same work is (in $\text{days}$):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo