$A$ track of $100\, m$ can be built by $7\, men$ or $10\, women$ in $70\, days.$ How many days will $14\, men$ and $20\, women$ take to build a track of $600\, m$?

  • A
    $15$
  • B
    $20$
  • C
    $25$
  • D
    $30$

Explore More

Similar Questions

Ajay and Sunil together can complete a piece of work in $10$ days,Sunil and Sanjay in $15$ days,and Sanjay and Ajay in $20$ days. They worked together for $6$ days,and then Ajay leaves. Sunil and Sanjay worked together for $4$ more days,and Sunil leaves. How long will Sanjay take to complete the remaining work? (in days)

Difficult
View Solution

$A$ takes three times as long as $B$ and $C$ together to do a job. $B$ takes four times as long as $A$ and $C$ together to do the work. If all the three,working together,can complete the job in $24$ days,then the number of days $A$ alone will take to finish the job is:

$A$ can do $\frac{1}{3}$ of a work in $5 \text{ days}$ and $B$ can do $\frac{2}{5}$ of the work in $10 \text{ days}$. In how many $\text{days}$ can both $A$ and $B$ together do the work?

$A$ team of $30$ men is supposed to do a work in $38$ days. After $25$ days,$5$ more men were employed and the work was finished one day earlier. How many days would it have been delayed if $5$ more men were not employed? (in days)

$2$ men alone or $3$ women alone can complete a piece of work in $4$ days. In how many days can $1$ woman and $1$ man together complete the same piece of work?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo