$A$ and $B$ can do a piece of work in $12$ days and $15$ days,respectively. They began to work together,but $A$ left after $4$ days. In how many more days would $B$ alone complete the remaining work?

  • A
    $\frac{20}{3}$
  • B
    $\frac{25}{3}$
  • C
    $6$
  • D
    $5$

Explore More

Similar Questions

$A, B$ and $C$ completed a work costing $Rs. 1800$. $A$ worked for $6$ days,$B$ for $4$ days and $C$ for $9$ days. If their daily wages are in the ratio of $5: 6: 4$,how much amount will be received by $A$ (in $Rs.$)?

$A, B$ and $C$ can complete a work in $2 \, h$. If $A$ does the job alone in $6 \, h$ and $B$ in $5 \, h$,how long will it take for $C$ to finish the job alone? (in $h$)

$20$ men can complete a piece of work in $16$ days. After $5$ days from the start of the work,some men left. If the remaining work was completed by the remaining men in $18 \frac{1}{3}$ days,how many men left after $5$ days from the start of the work?

$A, B$ and $C$ can complete a piece of work in $15, 30$ and $40$ days respectively. They started the work together,but $A$ left $2$ days before the completion of the work and $B$ left $4$ days before the completion of the work. In how many days was the work completed?

$A$ and $B$ working separately can do a piece of work in $9$ and $12$ days,respectively. If they work for a day alternately with $A$ beginning,the work would be completed in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo