$10$ men can finish a piece of work in $10$ days,whereas it takes $12$ women to finish it in $10$ days. If $15$ men and $6$ women undertake to complete the work,how many days will they take to complete it?

  • A
    $7$
  • B
    $5$
  • C
    $9$
  • D
    None of these

Explore More

Similar Questions

$A$ team of $30$ men is supposed to do a work in $38$ days. After $25$ days,$5$ more men were employed and the work was finished one day earlier. How many days would it have been delayed if $5$ more men were not employed? (in days)

$A$ and $B$ can do a piece of work in $12 \, \text{days}$ and $15 \, \text{days}$ respectively. They began to work together,but $A$ left after $4 \, \text{days}$. In how many more $days$ would $B$ alone complete the remaining work?

Three men,four women and six children can complete a work in $7$ days. $A$ woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in $7$ days?

Difficult
View Solution

If the wages of $45$ women amount to $Rs. 46575$ in $48$ days,how many men must work for $16$ days to receive $Rs. 17250$,given that the daily wage of a man is double that of a woman?

$A, B$ and $C$ together can finish a piece of work in $4$ days. $A$ alone can do it in $12$ days and $B$ alone in $18$ days. How many days will be taken by $C$ to do it alone?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo