$6$ men can complete a piece of work in $12$ days. $8$ women can complete the same piece of work in $18$ days,whereas $15$ children can complete the piece of work in $10$ days. $4$ men,$12$ women,and $20$ children work together for $2$ days. If only men were to complete the remaining work in $1$ day,how many men would be required?

  • A
    $36$
  • B
    $24$
  • C
    $18$
  • D
    Cannot be determined

Explore More

Similar Questions

$5$ men can prepare $10$ toys in $6$ days working $6$ hours a day. Then,in how many days can $12$ men prepare $16$ toys working $8$ hours a day? (in days)

$A$ and $B$ can do a job together in $7$ days. $A$ is $1\frac{3}{4}$ times as efficient as $B$. The same job can be done by $A$ alone in (in days):

Difficult
View Solution

$A$ works thrice as good as $B$ and is,therefore,able to finish a piece of work in $60 \text{ days}$ less than $B$. Find the time in which they can complete it,working together (in $\text{days}$).

Difficult
View Solution

$A$ and $B$ together can complete a work in $3$ days. They start together,but after $2$ days,$B$ left the work. If the work is completed after two more days,in how many days would $B$ alone do the work?

$A$ can finish a work in $12$ days and $B$ can do it in $15$ days. After $A$ had worked for $3$ days,$B$ also joined $A$ to finish the remaining work. In how many days will the remaining work be finished?

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo