$A$ certain number of persons can complete a piece of work in $55 \text{ days}$. If there were $6$ persons more,the work could be finished in $11 \text{ days}$ less. How many persons were originally there?

  • A
    $17$
  • B
    $24$
  • C
    $30$
  • D
    $22$

Explore More

Similar Questions

How many $days$ will $1648$ persons take to construct a dam,if $721$ persons can build the same in $48$ days?

$A$ and $B$ can do a piece of work in $20$ days and $12$ days respectively. $A$ started the work alone and then after $4$ days $B$ joined him until the completion of the work. How long did the work last? (in days)

Difficult
View Solution

$A$ and $B$ can together finish a work in $30$ days. They worked at it for $20$ days and then $B$ left. The remaining work was done by $A$ alone in $20$ more days. $A$ alone can finish the work in (in days):

If $x$ men can do a piece of work in $x$ days,then the number of days in which $y$ men can do the same work is (in days)

$A$ takes twice as much time as $B$ or thrice as much time as $C$ to finish a piece of work. Working together,they can finish the work in $2$ days. $B$ can do the work alone in (in days):

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo