$A$ can do a piece of work in $8$ days. $A$ undertook it for $Rs. 320$. With the help of $B$,he finishes the work in $6$ days. $B$'s share is (in $Rs.$):

  • A
    $80$
  • B
    $240$
  • C
    $100$
  • D
    $120$

Explore More

Similar Questions

Anu can complete a work in $10$ days. Manu is $25\%$ more efficient than Anu,and Sonu is $60\%$ more efficient than Manu. Working together,how long would they take to finish the job? (in days)

$A$ and $B$ undertake a piece of work for $Rs. 250$. $A$ alone can do that work in $5$ days and $B$ alone can do that work in $15$ days. With the help of $C$,they finish the work in $3$ days. If everyone gets paid in proportion to the work done by them,the amount $C$ will get is (in $Rs.$)

Difficult
View Solution

$A$ and $B$ working separately can do a piece of work in $9$ and $12$ days,respectively. If they work for a day alternatively with $A$ beginning,the work would be completed in (in days):

$A$ and $B$ together can do a piece of work in $10$ days. $A$ alone can do it in $30$ days. The time in which $B$ alone can do it is (in days):

$A, B$ and $C$ can do a piece of work in $16, 32$ and $48$ days,respectively. They started working together,but $C$ left after working $4$ days and $B$ left $2$ days before the completion of the work. The total number of days taken for the completion of the work was (in days):

Difficult
View Solution

Vedclass Products

For Students

Vedclass Test Series

Mock tests in real JEE/NEET style with performance analysis. 5-day free trial.

Start Free Trial
For Teachers

Exam Paper Generator

Generate Set A/B/C/D exam papers from 7.5L+ questions in 2 minutes. 3 chapters free.

Try Free
For Institutes

Online Exam Module

Live online exams with unlimited students, 360° analytics & white-label branding.

See Demo